electric · captured Jun 11, 2026
Feb 9, 2026
service Dec 31, 2025 → Jan 9, 2026
Vendor
Reliant Energy
Property
2704 CDMX
Due date
Feb 25, 2026
Amount due
$8,703.56
Current charges
$628.69
Previous balance
$7,948.74
Payments received
$0.00
Tax
$47.92
▸ 11 charge lines
- CONSUMPTIONActual Consumption * Price$358.28
- NODAL_CONGNodal Congestion Charge-$5.23
- TDSP_CUSTTDSP Customer Charge$3.34
- DEL_POINTDelivery Point Charge$6.39
- DIST_CRFDistribution Cost Recovery Factor$24.88
- EECRFEnergy Efficiency Cost Recovery Factor (EECRF)$1.16
- DUOSDistribution Charge (DUOS)$122.90
- TRANS_CRFTransmission Cost Recovery Factor$69.05
- SPEC_TAXSpecial Tax$5.81
- CITY_SALES_TAXCity Sales Tax 1%$5.81
- STATE_SALES_TAXState Sales Tax 6.25%$36.30